Spring Road construction begins

von Gary Gardiner

Spring Road construction begins


Spring Road Construction First Phase begins Monday

The City of Westerville is making the following Improvements:



Total reconstruction of the existing pavement and new curbing
Installation of the new curbing will require a 2-foot strip of each driveway to be removed and replaced (immediately adjacent to the curb)

Detour and Schedule:


No detour, through traffic maintained but alternate route recommended

Phase 1 (southbound lanes):



Inlets & Curb: late May - mid June
Drive Aprons: mid June
Roadway: mid June - late June
Lawn Restoration: mid August

Phase 2 (northbound lanes):



Inlets & Curb: early July - mid July
Drive Aprons: mid July - late July
Roadway: late July - early August
Lawn Restoration: mid August

Fact Sheet at City Site